C&D Foods Warehouse
C&D Foods, Edgeworthstown, Co Longford |
| |
|
|
|
|
Client |
C&D Foods |
Duration |
10 months |
|
Main Contractor |
GEM Construction |
Architect |
Design & Build – Dixon McGaver Nolan |
|
|
Value |
€6 million |
Sector |
Commercial/Industrial
|
|
6500m² Warehouse 12m to eaves, which includes 860m² Coldstore & 270m² Tempering Room, c/w all necessary plant room
Summary of the works include:
- Direction of overhead 35KV ESB lines
- Relocation of external waterways to perimeter pipe drainage
- Site Clearance
- Min. 600mm hardcore base on 1000g tarram
- 3.5 x 3.5 x 1.5 concrete bases for steel stanchion
- Precast perimeter walls between stanchion
- 825m² Coldstore construction for cold room
- 270m² construction of Tempering room
- 200mm concrete floor slab, main floor c/w railway lines for track storage facilities
- Wall & roof cladding c/w roof smoke vents
- Standby underground lagoon for firefighting services for 600m³ water storage
- Perimeter Palisade fence
- 200mm concrete yard & 8nr. special truck dock levellers
- Utilities (ESB, Gas, Water, Eircom)
- Construction of new office accommodation along side new warehouse
|
| |
|
|
|
|
 |
Head Office:
Athlone Road,
Longford,
Co. Longford
T: +353 43 3345217
F: +353 43 3341854
E: info@gemgroup.ie |
Dublin Office:
Unit 2 Block 4B,
Blanchardstown
Corporate Park, Dublin 15
T: +353 1 8850432
F: +353 1 8850496
E: info@gemgroup.ie |
UK Office:
Mere House, Brook Street,
Knutsford, Cheshire,
WA16 8GP
T: +44 1565 752412
F: +44 1565 752121
E: info@gemgroup.co.uk |
|